Water District Mainline Replacement Project to Beg...
searchSearch
Search

East Gig Harbor Water District:


The Goodman, 89th Street and Randall Drive Water Main Pipe replacement project will begin.

1. Project should begin the week of Oct 12th


2. The mainline replacement will take approximately a month.


3. The individual service to customers meters might take an additional week.


4. There will be traffic control flagging during construction please be patient.


5. Once again that section of mainline Pipe is roughly 70yrs old and this is a preventative upgrade so we don’t experience issues in the future.


6. There will only be water service disruption during the last 2 week Individual service hookup period and those will be individually addressed.

Those disruptions will be minimal during the day of your individual cutover to the new mainline.